Workstation
A Workstation is a physical location or machine where manufacturing operations are performed. Workstations are used to plan capacity and track production costs.
Creating a Workstation
- Go to Manufacturing > Workstation and click New.
- Enter the Workstation Name (e.g., "Assembly Line 1", "CNC Machine 3").
- Optionally set:
- Production Capacity: Maximum units per day
- Hourly Rate (Electricity): Electricity cost per hour
- Hourly Rate (Consumables): Consumables cost per hour
- Hourly Rate (Rent): Rent/space cost per hour
- Hourly Rate (Wages): Labor cost per hour
- Hourly Rate: Total operating cost per hour (sum of above or custom)
- Enter a Description of the workstation.
- Click Save.
Workstation Types
| Type | Examples |
|---|---|
| Manual | Assembly bench, painting station |
| Machine | CNC machine, injection molding, press |
| QC Station | Quality inspection station |
| Packing Station | Packaging and labeling station |
Workstation Costing
The workstation Hourly Rate contributes to the product cost:
- Each operation in the BOM has a time estimate (in minutes).
- Operation cost = (Time in minutes ÷ 60) × Workstation Hourly Rate.
- The sum of all operation costs is added to the product's manufacturing cost.
Workstation Capacity
- Set the Production Capacity to define how many units can be produced per day at this workstation.
- Production planning uses this to schedule work orders and avoid overloading workstations.